What criterion does the product owner use to sequence the product backlog?
- A . Business priority
- B . Resource availability
- C . Relative effort
- D . Complexity
Which of the following tools can support you in managing requirements and software development for implementation projects? Note: There are 2 correct answers to this question
- A . SAP Focused Run
- B . Focused Build for SAP Solution Manager
- C . Focused Insights for SAP Solution Manager
- D . SAP Cloud ALM
What is Scrum of Scrums?
- A . Frequent inspection of code and configuration prior to quality gates
- B . Integration meeting among the various Scrum teams
- C . Mechanism for gathering and validating requirements
- D . Alternative to regular Scrum process for smaller teams
Which of the following are cornerstones of SAP’s security strategy? Note: There are 3 correct answers to this question
- A . Secure Company
- B . Secure Projects
- C . Secure Operations
- D . Secure Infrastructure
- E . Secure Products
When working with an Agile approach, what is the minimum planning requirement expected at the beginning of the Realize phase?
- A . Realize phase scope, planning, and budget should be completed and final.
- B . Release plan and sprint ceremony guidelines should be finalized.
- C . Sprint planning and sprint durations should be defined for the first 2 to 3 sprints.
- D . User stories on product backlog should be in ready state for the first 2 to 3 sprints.
What tool would you use for managing project tasks and Solution Documentation when implementing SAP S/4HANA Cloud, public edition?
- A . SAP Support Portal
- B . SAP Roadmap Viewer
- C . SAP Transformation Navigator
- D . SAP Cloud ALM
Which activity helps the project team identify and add user stories to the backlog?
- A . Planning the User Acceptance Testing
- B . Conducting the fit-to-standard workshop
- C . Preparing a project schedule and budget
- D . Assessing project risks and issues
Which new project roles are introduced with the SAP Activate methodology for the Agile delivery approach, compared to Waterfall? Note: There are 2 correct answers to this question.
- A . Scrum master
- B . Product owner
- C . Design thinking coach
- D . Integration lead
Which additional scope option does the strategic advisory service for cloud analytics offer? Note: There are 2 correct answers to this question
- A . Extended package
- B . SAP S/4HANA for central finance
- C . Baseline package
- D . SAP Activate methodology for the Intelligent Enterprise